A pre-handover checklist for a Melton South home

The items that get measured rather than described.

Melton South 3338 · 4 February 2026

Fully licensed & accredited

  • Building & Plumbing Commission (VIC) Building & Plumbing Commission
  • Australian Society of Building Consultants Australian Society of Building Consultants
  • Strata Community Association Strata Community Association
  • Building Dispute Practitioners Society Building Dispute Practitioners Society

In short: Handover here is about numbers: crack widths, wall tolerances and fixing methods.

Book before the date

Practical completion is your last leverage. A week's notice is enough.

Slab cracking

Measured, then categorised. Ours came in between 2mm and 4mm, over tolerance.

Wall straightness

Bow is checked against a 5mm tolerance, not judged by eye.

Cappings

Fixed from above is not the detail. It has to be fixed the way the system requires.

Plumbing

Mixers checked for leaks, and taps operated to listen for water hammer.

Sealing

Wall, eave, door and window joints caulked as required.

Written by our local inspection team from work carried out in Melton South. Licensed building practitioners.

Guides

More pci / handover guides for Melton South

All guides →

Book a building inspection in Melton South

Instant online pricing for Melton South, or contact the booking team.

FAQ

Questions Melton South owners ask about this

How long on site?

Two to three hours.

Reinspection?

Yes, before settlement.

Excluded?

Live circuits, pressure tests, system commissioning and appliance checks.

Will the builder engage?

Generally, because each item cites a number.