The last inspection where the builder carries the cost, and the one where things finally get measured.
Melton South handovers produce numbers rather than opinions: slab cracks between 2mm and 4mm, walls outside the 5mm bow tolerance, and cappings fixed from the wrong side.

Annotated findings from Pre-handover (PCI) inspections on Melton South builds. Client addresses withheld.




1Bored piersAfter boring and cage placement, ahead of concrete
2Slab pre-pourThe day before the pour, with steel, pods and formwork open
3FrameOnce frame and trusses are up and the roof is on, before sarking
4Lock-up (pre-plaster)After roof, cladding and external doors, before plaster
5FixingAfter mouldings, doors and joinery, before the painter
6WaterproofingOnce the membrane is on and cured, before tilingInstant online pricing, or talk to the booking team on 1300 471 805.
Immediately. Your position is strongest before signing at practical completion.
No. Cracks between 2mm and 4mm sit outside tolerance, which is why they are measured rather than described.
A knock in the pipework when a tap is shut. It signals pressure or restraint problems in the plumbing.
Yes, a reinspection works through the list before settlement.
Energising circuits, pressure testing, commissioning, appliance and garage door safety testing, and anything concealed.
Two to three hours, and longer on a double storey.